Problem 1 ・ Question 1 / 13

Which analysis should be carried out first when developing a business continuity plan?

View explanation

The BIA establishes the critical processes, the impact of an outage, the dependencies and the recovery priorities.

Problem 1 ・ Question 2 / 13

What does RTO represent?

View explanation

RTO is the target time that can be tolerated between the loss of service and its restoration.

Problem 1 ・ Question 3 / 13

What does an RPO of four hours mean?

View explanation

RPO expresses, in time, the extent of data loss tolerated as the point of recovery.

Problem 1 ・ Question 4 / 13

Who is the most important source of information for a BIA?

View explanation

Process owners understand best the impact of an outage, the manual workarounds, the dependencies and the recovery priorities.

Problem 1 ・ Question 5 / 13

What characterises a hot site?

View explanation

A hot site suits a short RTO, but it is generally expensive.

Problem 1 ・ Question 6 / 13

Which test gives the strongest confirmation that a disaster recovery plan works?

View explanation

A test involving real processing verifies the technology, the procedures, the people and the dependencies together.

Problem 1 ・ Question 7 / 13

What is the best way to confirm that backup controls are effective?

View explanation

Beyond a successful backup, it must be tested that the data can be restored correctly when needed.

Problem 1 ・ Question 8 / 13

Two data centres in the same area face the same flood risk. What is the most appropriate measure?

View explanation

Enough geographic separation is needed to avoid correlated regional disasters.

Problem 1 ・ Question 9 / 13

What matters most in a crisis communication plan?

View explanation

Set out who is authorised, the contacts and the alternative channels so that consistent, accurate information is provided in good time.

Problem 1 ・ Question 10 / 13

What is the main benefit of a tabletop exercise?

View explanation

Discussion following a scenario uncovers gaps in communication, decision-making, responsibility and the plan.

Problem 1 ・ Question 11 / 13

What is the main role of a UPS against power failure?

View explanation

A UPS rides through momentary interruptions and buys time to shut down or switch to emergency power.

Problem 1 ・ Question 12 / 13

What is the most important trigger for updating a business continuity plan?

View explanation

Reflect changes in the organisation and its dependencies, test results and the lessons of incidents in the plan.

Problem 1 ・ Question 13 / 13

Which backup design best improves resilience against ransomware?

View explanation

Separate, immutable copies reduce the risk of an attacker encrypting or deleting them at the same time.